NYC Environmental Protection Dept.: Phase 2 of Massive Queens Sewer Program Completed in Maspeth
October 09, 2024
October 09, 2024
NEW YORK, Oct. 9 -- The New York City Department of Environmental Protection issued the following news on Oct. 7, 2024:
* * *
Micro-tunneling techniques successful in reducing disruptions to businesses, residents and traffic during $106 million project
Over $200 million of drainage and local water main upgrades in total
* * *
The NYC Department of Environmental Protection (DEP) and the NYC Department of Design and Construction (DDC . . .
* * *
Micro-tunneling techniques successful in reducing disruptions to businesses, residents and traffic during $106 million project
Over $200 million of drainage and local water main upgrades in total
* * *
The NYC Department of Environmental Protection (DEP) and the NYC Department of Design and Construction (DDC . . .